Contact Us for help
Follow on Facebook Follow on X Follow on LinkedIn Follow on Spotify Follow on iTunes
Join the Planning Geek Facebook Group
Jump to content

4 year rule / class q


WM

Recommended Posts

Hi there 

If class q permission was granted before 24th April 2024 and the building substantially completed before this date does the 4 year rule apply to the building work you have done?  

 

Thanks   

 

Link to comment
Share on other sites

  • Administrators

The 4 year rule doesn't apply if you have permission granted under Class Q as long as you complete within 3 years of the decision notice. 

Unless I have misunderstood the question 

Link to comment
Share on other sites

Create an account or sign in to comment

You need to be a member in order to leave a comment

Create an account

Sign up for a new account in our community. It's easy!

Register a new account

Sign in

Already have an account? Sign in here.

Sign In Now
×
  • Create New...